Footers getting poured today
Barring unforeseen changes or impediments, what time frame are we looking at from this point forward?
Thought someone said early December was the target completion date
Disagree. Barring any unforeseen hold-ups, there's no reason a pre-engineered building can't be ready to occupy in 4 months, especially if the contractors schedule 2 shifts/day.I am by no means an expert. But I'd be hard-pressed to believe the building will be ready for use by Dec 1.
I think its more realistic for them to have a covered structure by Dec 1 with the finishing work taking place over the winter.
I am by no means an expert. But I'd be hard-pressed to believe the building will be ready for use by Dec 1.
I think its more realistic for them to have a covered structure by Dec 1 with the finishing work taking place over the winter.
Ofcourse everyone can watch this on the two cams set up.
There aren't any cameras set upMark, please post the links if possible. Thanks.
If it is a pre-engineered building it will not take that long to get it constructed.
There aren't any cameras set up
What we're seeing in that photo is the foundation, the crush-n-run on the inside will be used to back fill the excavated areas around the foundation and to level/grade the surface.
I would imagine the next step would be to pour the pad, unless the cranes being used to place the steel are so heavy that they want to erect the framing prior to pouring the pad. The rebar you see with orange caps could be anchor bolts, but I can't tell if it's them or just rebar. If they're anchor bolts, you'll have sill plates, drilled out and placed over the anchor bolts, then nutted down on top of them.
We're very close to seeing some action ladies and gents. From an outside perspective, erecting the structure happens almost the fastest in the process and looks like the most is getting done.
220..221, whatever it takesWhat we're seeing in that photo is the foundation, the crush-n-run on the inside will be used to back fill the excavated areas around the foundation and to level/grade the surface.
I would imagine the next step would be to pour the pad, unless the cranes being used to place the steel are so heavy that they want to erect the framing prior to pouring the pad. The rebar you see with orange caps could be anchor bolts, but I can't tell if it's them or just rebar. If they're anchor bolts, you'll have sill plates, drilled out and placed over the anchor bolts, then nutted down on top of them.
We're very close to seeing some action ladies and gents. From an outside perspective, erecting the structure happens almost the fastest in the process and looks like the most is getting done.
I cant remember that last project we did on our campus that didnt have a camera and a web site to promote the project. its almost a zero cost to the project and in this case its a project that has way more people wondering about it and its a recruiting tool as well.