Also in Engineering/Consulting: yeah how would you like that fee on your books $2m for cut and paste yeah that will help the bottom line. I think ottomets is right though parsons is probably there for the tunnel review they do a ton of municipal tunneling jobs...#7 subway extension to name one huge one. There are definately challenges with the tunnel option.
If they did go with a tunnel Ive always thought that a drilled soldier or slurry wall approach where you build the walls and roof of the tunnel at grade before excavating below with standard non tbm equipment makes sense for the soil conditions. Coastal cities with similar soil conditions sometimes use this method.
Id also put it under Townsend street with the walls on/off ramps installed in grassy areas outside the current roadway. You could close one block at a time to install the roof framing then excavate below the roof with active traffic above. Least impact to 81 (torn down after new is complete) and city traffic flow is adjustable around sections of Townsend. Many streets that used to cross Townsend before orig 81 construction no longer do, limiting crossflow costs that force weekend/offpeak work to Adams Harrison genesee and Erie.
I think this approach would also reduce cost of what they proposed as the tunnel budget originally.
Otherwise for the most part the other options make more sense for money. in a perrfect world where money was not part of it tunnel is great but if we don't have a way to pay for the tunnel were just spending time and escalation budget.
$2m please...
Interesting.
Were the original tunnel estimates made with the expectation that boring machines would be used (as opposed to the cut and cover method/top down method it appears to me that you are talking about)?
Tunnel - Wikipedia
Cut-and-cover[edit]
https://upload.wikimedia.org/wikipedia/commons/thumb//f7/Paris_Metro_construction_03300288-3.jpg/220px-Paris_Metro_construction_03300288-3.jpg
Cut-and-cover construction of the
Paris Métro in
France
Cut-and-cover is a simple method of construction for shallow tunnels where a
trench is excavated and
roofed over with an overhead support system strong enough to carry the load of what is to be built above the tunnel. Two basic forms of cut-and-cover tunnelling are available:
- Bottom-up method: A trench is excavated, with ground support as necessary, and the tunnel is constructed in it. The tunnel may be of in situ concrete, precast concrete, precast arches, or corrugated steel arches; in early days brickwork was used. The trench is then carefully back-filled and the surface is reinstated.
- Top-down method: Side support walls and capping beams are constructed from ground level by such methods as slurry walling or contiguous bored piling. Then a shallow excavation allows making the tunnel roof of precast beams or in situ concrete. The surface is then reinstated except for access openings. This allows early reinstatement of roadways, services and other surface features. Excavation then takes place under the permanent tunnel roof, and the base slab is constructed.
Shallow tunnels are often of the cut-and-cover type (if under water, of the immersed-tube type), while deep tunnels are excavated, often using a
tunnelling shield. For intermediate levels, both methods are possible.
Large cut-and-cover boxes are often used for underground
metro stations, such as
Canary Wharf tube station in London. This construction form generally has two levels, which allows economical arrangements for ticket hall, station platforms, passenger access and emergency egress, ventilation and smoke control, staff rooms, and equipment rooms. The interior of Canary Wharf station has been likened to an underground cathedral, owing to the sheer size of the excavation. This contrasts with many traditional stations on
London Underground, where bored tunnels were used for stations and passenger access. Nevertheless, the original parts of the London Underground network, the Metropolitan and District Railways, were constructed using cut-and-cover. These lines pre-dated electric traction and the proximity to the surface was useful to ventilate the inevitable smoke and steam.
A major disadvantage of cut-and-cover is the widespread disruption generated at the surface level during construction. This, and the availability of electric traction, brought about London Underground's switch to bored tunnels at a deeper level towards the end of the 19th century.
Boring machines[edit]
Main article:
Tunnel boring machine

A workman is dwarfed by the
tunnel boring machine used to excavate the
Gotthard Base Tunnel (
Switzerland), the world's longest.
Tunnel boring machines (TBMs) and associated back-up systems are used to highly automate the entire tunnelling process, reducing tunnelling costs. In certain predominantly urban applications, tunnel boring is viewed as quick and cost effective alternative to laying surface rails and roads. Expensive
compulsory purchase of buildings and land, with potentially lengthy planning inquiries, is eliminated. Disadvantages of TBMs arise from their usually large size - the difficulty of transporting the large TBM to the site of tunnel construction, or (alternatively) the high cost of assembling the TBM on-site, often within the confines of the tunnel being constructed.
There are a variety of TBM designs that can operate in a variety of conditions, from hard rock to soft water-bearing ground. Some types of TBMs, the bentonite slurry and earth-pressure balance machines, have pressurised compartments at the front end, allowing them to be used in difficult conditions below the
water table. This pressurizes the ground ahead of the TBM cutter head to balance the water pressure. The operators work in normal air pressure behind the pressurised compartment, but may occasionally have to enter that compartment to renew or repair the cutters. This requires special precautions, such as local ground treatment or halting the TBM at a position free from water. Despite these difficulties, TBMs are now preferred over the older method of tunnelling in compressed air, with an air lock/decompression chamber some way back from the TBM, which required operators to work in high pressure and go through decompression procedures at the end of their shifts, much like
deep-sea divers.
In February 2010, Aker Wirth delivered a TBM to Switzerland, for the expansion of the
Linth–Limmern Power Stations located south of
Linthal in the
canton of Glarus. The borehole has a diameter of 8.03 metres (26.3 ft).
[9] The four TBMs used for excavating the 57-kilometre (35 mi)
Gotthard Base Tunnel, in
Switzerland, had a diameter of about 9 metres (30 ft). A larger TBM was built to bore the Green Heart Tunnel (Dutch: Tunnel Groene Hart) as part of the
HSL-Zuid in the Netherlands, with a diameter of 14.87 metres (48.8 ft).
[10] This in turn was superseded by the
Madrid M30 ringroad,
Spain, and the
Chong Ming tunnels in
Shanghai,
China. All of these machines were built at least partly by
Herrenknecht. As of August 2013, the world's largest TBM is "
Big Bertha", a 57.5-foot (17.5 m) diameter machine built by
Hitachi Zosen Corporation, which is digging the
Alaskan Way Viaduct replacement tunnel in
Seattle, Washington (US).
[11]
...